Identify, in order, the six steps basic to both PERT and CPM.

Correct Answer

verifed

verified

1. Define the project and prepare the WB...

View Answer

The Beta distribution is used in project management to


A) calculate slack on activities not on the critical path.
B) calculate the probability that a project will be completed within its budget.
C) calculate pessimistic and optimistic activity times.
D) determine which activity should be crashed.
E) none of the above.

Correct Answer

verifed

verified

A network consists of the activities in the following list. Times are given in weeks.  Activity  Preceding  Duration  A 8 B 3 C  A 7 D  A, B 3 E  C 4 F  D 6\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Preceding } & \text { Duration } \\\hline \text { A } & - - & 8 \\\hline \text { B } & - - & 3 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { A, B } & 3 \\\hline \text { E } & \text { C } & 4 \\\hline \text { F } & \text { D } & 6 \\\hline\end{array} a. Draw the network diagram. b. Calculate the ES, EF, LS, LF, and Slack for each activity. c. What is project completion time?

Correct Answer

verifed

verified

What are the advantages of using PERT and CPM?

Correct Answer

verifed

verified

The advantages include its usefulness fo...

View Answer

Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut two days from the project's duration, activity ________ should be crashed, adding ________ to the total project cost.  Activity  Normal Time  Normal Cost  Crash Time  Crash Cost D5 days $6,0003 days $8,000E8 days $4,0004 days $6,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \text { Crash Time } & \text { Crash Cost } \\\hline \mathrm { D } & 5 \text { days } & \$ 6,000 & 3 \text { days } & \$ 8,000 \\\hline \mathrm { E } & 8 \text { days } & \$ 4,000 & 4 \text { days } & \$ 6,000 \\\hline\end{array}


A) D; $2,000
B) D; $1,000
C) E; $500
D) E; $1,000
E) E; $6,000

Correct Answer

verifed

verified

Which of the following statements regarding critical paths is true?


A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project, there can be multiple critical paths, all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.

Correct Answer

verifed

verified

If an activity whose normal duration is 55 days can be shortened to 50 days for an added cost of $45,000, the crash cost per period is


A) $9,000.
B) $500.
C) $900.
D) $4,500.
E) $45,000.

Correct Answer

verifed

verified

Ethical issues that may arise in projects large and small due to


A) fair selection of contractors.
B) accurate expense reports.
C) enforcement of safety or health standards.
D) pressure to mask delays with false status reports.
E) adherence to quality standards.

Correct Answer

verifed

verified

Every network has at least one critical path.

Correct Answer

verifed

verified

________ is the amount of time an individual activity in a network can be delayed without delaying the entire project.

Correct Answer

verifed

verified

Shortening the project's duration by deleting unnecessary activities is called "project crashing."

Correct Answer

verifed

verified

What are the earliest activity start time and latest activity start time, and how are they computed?

Correct Answer

verifed

verified

The earliest start time is the earliest ...

View Answer

In project management, crashing an activity must consider the impact on all paths in the network.

Correct Answer

verifed

verified

A network consists of the following list. Times are given in weeks.  Activity  Preceding  Optimistic  Probable  Pessimistic A51114B339C61014DA,B357EB4611 F C6813 G D,E246HF339\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Preceding } & \text { Optimistic } & \text { Probable } & \text { Pessimistic } \\\hline \mathrm { A } & - - & 5 & 11 & 14 \\\hline \mathrm { B } & - & 3 & 3 & 9 \\\hline \mathrm { C } & - - & 6 & 10 & 14 \\\hline \mathrm { D } & \mathrm { A } , \mathrm { B } & 3 & 5 & 7 \\\hline \mathrm { E } & \mathrm { B } & 4 & 6 & 11 \\\hline \text { F } & \mathrm { C } & 6 & 8 & 13 \\\hline \text { G } & \mathrm { D } , \mathrm { E } & 2 & 4 & 6 \\\hline \mathrm { H } & \mathrm { F } & 3 & 3 & 9 \\\hline\end{array} a. Draw the network diagram. b. Calculate the expected duration and variance of each activity. c. Calculate the expected duration and variance of the critical path. d. Calculate the probability that the project will be completed in less than 28 weeks.

Correct Answer

verifed

verified

(a) blured image (b,c)
blured image (d) z =...

View Answer

PERT calculations typically include the duration variance of each activity. What is the purpose of this calculation-what's the role of variances in PERT analysis?

Correct Answer

verifed

verified

The activity variances influence the pro...

View Answer

Describe some of the challenges faced in the construction of the new 11-story building at Arnold Palmer Hospital in Orlando, Florida.

Correct Answer

verifed

verified

Prior to beginning actual construction, ...

View Answer

WBS stands for which of the following project management tools?


A) Work Break Schedule
B) Work Breakdown Status
C) Work Breakdown Schedule
D) Work Breakdown Structure
E) Week Breakdown Schedule

Correct Answer

verifed

verified

________ is a network technique using only one time factor per activity that enables managers to schedule, monitor, and control large and complex projects.

Correct Answer

verifed

verified

Critical p...

View Answer

Which of the following statements concerning CPM activities is false?


A) The early finish of an activity is the early start of that activity plus its duration.
B) The late finish is the earliest of the late start times of all successor activities.
C) The late start of an activity is its late finish less its duration.
D) The late finish of an activity is the earliest late start of all preceding activities.
E) The early start of an activity is the latest early finish of all preceding activities.

Correct Answer

verifed

verified

What is a project organization?

Correct Answer

verifed

verified

A project organization is a fo...

View Answer