Correct Answer
verified
View Answer
Multiple Choice
A) calculate slack on activities not on the critical path.
B) calculate the probability that a project will be completed within its budget.
C) calculate pessimistic and optimistic activity times.
D) determine which activity should be crashed.
E) none of the above.
Correct Answer
verified
Essay
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) D; $2,000
B) D; $1,000
C) E; $500
D) E; $1,000
E) E; $6,000
Correct Answer
verified
Multiple Choice
A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project, there can be multiple critical paths, all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.
Correct Answer
verified
Multiple Choice
A) $9,000.
B) $500.
C) $900.
D) $4,500.
E) $45,000.
Correct Answer
verified
Multiple Choice
A) fair selection of contractors.
B) accurate expense reports.
C) enforcement of safety or health standards.
D) pressure to mask delays with false status reports.
E) adherence to quality standards.
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) Work Break Schedule
B) Work Breakdown Status
C) Work Breakdown Schedule
D) Work Breakdown Structure
E) Week Breakdown Schedule
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Multiple Choice
A) The early finish of an activity is the early start of that activity plus its duration.
B) The late finish is the earliest of the late start times of all successor activities.
C) The late start of an activity is its late finish less its duration.
D) The late finish of an activity is the earliest late start of all preceding activities.
E) The early start of an activity is the latest early finish of all preceding activities.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer