Filters
Question type

  -According to the table above.What are the net requirements Front Leg Assemblies in Week 4 -According to the table above.What are the net requirements Front Leg Assemblies in Week 4

Correct Answer

verifed

verified

Gross requirements in an MRP record can be met by inventory from previous weeks, scheduled receipts, or planned receipts.

Correct Answer

verifed

verified

Consider the product structure tree shown below: Consider the product structure tree shown below:   With a beginning inventory of twenty for all components on level one, five for all components on level two, and zero for all components on level three and finished items, how many more K's than F's are needed to produce 25 product X's? A) 15 B) 10 C) 5 D) 0 With a beginning inventory of twenty for all components on level one, five for all components on level two, and zero for all components on level three and finished items, how many more K's than F's are needed to produce 25 product X's?


A) 15
B) 10
C) 5
D) 0

Correct Answer

verifed

verified

Which step in the top down model of manufacturing planning and control system comes after sales and operations planning?


A) master scheduling
B) material requirements planning
C) production activity control
D) vendor order management

Correct Answer

verifed

verified

Which of these correctly explains the relationship between available to promise inventory and the master production schedule for any week beyond the first week of the schedule when production is scheduled? Note that ATP is available to promise, MPS is master production schedule, EI is ending inventory, and OB is orders booked.


A) ATP = MPS + OB\sum O B
B) MPS = ATP + OB\sum O B
C) ATP = EI + MPS - OB\sum O B
D) MPS = OB\sum O B + ATP - EI

Correct Answer

verifed

verified

________ translates the master schedule for final products into detailed material requirements.

Correct Answer

verifed

verified

Material r...

View Answer

There are 50 units in inventory at the start of week 1 for this company, which runs a lot-for-lot MRP system. There is a one week lead time for all shipping and production quantities regardless of volume. What are the quantities of the planned orders for this item for the first six weeks? 12345678 Gross Requirements 50203040 Scheduled receipts  Projected ending  Inventory  Net Requirements  Planned Receipts  Planned Orders \begin{array} { | l | c | c | c | c | c | c | c | c | } \hline & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 \\\hline \text { Gross Requirements } & 50 & 20 & 30 & & 40 & & & \\\hline \text { Scheduled receipts } & & & & & & & & \\\hline \text { Projected ending } & & & & & & & & \\\hline \text { Inventory } & & & & & & & & \\\hline \text { Net Requirements } & & & & & & & & \\\hline \text { Planned Receipts } & & & & & & & & \\\hline \text { Planned Orders } & & & & & & & & \\\hline\end{array}


A) 20, 30, 0, 40, 0, 0
B) 35, 0, 60, 0, 0, 0
C) 5, 30, 0, 40, 20, 0
D) 35, 0, 0, 40, 20, 0

Correct Answer

verifed

verified

There are six jobs that are awaiting processing at a machining center. The jobs are shown in the table with their processing time and scheduled completion time. Schedule the jobs by earliest due date and the critical ratio rule and calculate average lateness for all the jobs. Which scheduling technique performs BEST?  Job  Process Time  Due Time  A 1225 B 832 C 1540 D 1015 E 2027 F 1746\begin{array} { | c | c | c | } \hline \text { Job } & \text { Process Time } & \text { Due Time } \\\hline \text { A } & 12 & 25 \\\hline \text { B } & 8 & 32 \\\hline \text { C } & 15 & 40 \\\hline \text { D } & 10 & 15 \\\hline \text { E } & 20 & 27 \\\hline \text { F } & 17 & 46 \\\hline\end{array}

Correct Answer

verifed

verified

Earliest Due Date
\[\begin{array} { | c ...

View Answer

Given the forecast and booked orders shown in the table, and a beginning inventory of 0, what is the available to promise inventory for period 3? There are no LOT quantity constraints.  Period 1234 Forecasted Demand 1001009090 Booked Orders 103875421 Projected ending inventory  Master production schedule  Available to Promise \begin{array} { | l | c | c | c | c | } \hline \text { Period } & 1 & 2 & 3 & 4 \\\hline \text { Forecasted Demand } & 100 & 100 & 90 & 90 \\\hline \text { Booked Orders } & 103 & 87 & 54 & 21 \\\hline \text { Projected ending inventory } & & & & \\\hline \text { Master production schedule } & & & & \\\hline \text { Available to Promise } & & & & \\\hline\end{array}


A) 0
B) 12
C) 24
D) 36

Correct Answer

verifed

verified

The table shows a master schedule for end item Z that is produced according to the product structure tree shown below. Beginning inventories and lead times for components of Z are given in the table. The lot sizes for A, B, and C are 100 units and an L4L rule for E. Complete a materials requirement plan for components A, B, and C.  Period 123456 MPS Qty 000250275275\begin{array} { | l | c | c | c | c | c | c | } \hline \text { Period } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { MPS Qty } & 0 & 0 & 0 & 250 & 275 & 275 \\\hline\end{array}  The table shows a master schedule for end item Z that is produced according to the product structure tree shown below. Beginning inventories and lead times for components of Z are given in the table. The lot sizes for A, B, and C are 100 units and an L4L rule for E. Complete a materials requirement plan for components A, B, and C.   \begin{array} { | l | c | c | c | c | c | c | }  \hline \text { Period } & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline \text { MPS Qty } & 0 & 0 & 0 & 250 & 275 & 275 \\ \hline \end{array}     \begin{array} { | l | c | c | c | c | c | }  \hline \text { Component } & \text { A } & \text { B } & \text { C } & \text { D } & \text { E } \\ \hline \text { Lead Time } & 1 & 2 & 2 & 2 & 1 \\ \hline \text { Beginning Inv } & 50 & 75 & 100 & 15 & 40 \\ \hline \end{array}  Component  A  B  C  D  E  Lead Time 12221 Beginning Inv 50751001540\begin{array} { | l | c | c | c | c | c | } \hline \text { Component } & \text { A } & \text { B } & \text { C } & \text { D } & \text { E } \\\hline \text { Lead Time } & 1 & 2 & 2 & 2 & 1 \\\hline \text { Beginning Inv } & 50 & 75 & 100 & 15 & 40 \\\hline\end{array}

Correct Answer

verifed

verified

Determine a schedule for these jobs using the critical ratio criterion and calculate the average lateness. Then develop an earliest due date sequence and calculate average lateness.  Job  Process Time  Due Date  Job 1 1523 Job 2 715 Job 3 1234 Job 4 1728 Job 5 1127\begin{array} { | c | c | c | } \hline \text { Job } & \text { Process Time } & \text { Due Date } \\\hline \text { Job 1 } & 15 & 23 \\\hline \text { Job 2 } & 7 & 15 \\\hline \text { Job 3 } & 12 & 34 \\\hline \text { Job 4 } & 17 & 28 \\\hline \text { Job 5 } & 11 & 27 \\\hline\end{array}

Correct Answer

verifed

verified

blured imageblured imageblured imageblured imageblured imageCritical Ratio Sequence
\[\begin{array} ...

View Answer

  -According to the table above.What is the planned order for whiskers in Week 2? -According to the table above.What is the planned order for whiskers in Week 2?

Correct Answer

verifed

verified

A time-phased planning approach that uses planned orders at the point of demand to determine forecasted demand at the source level is:


A) RFID.
B) EDD.
C) DRP.
D) MRP.

Correct Answer

verifed

verified

Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1? 12345 Gross Requirements 400500300 Scheduled receipts 00000 Projected ending Inventory 100100 Net Requirements  Planned Receipts 300 Planned Orders \begin{array} { | l | c | c | c | c | c | } \hline & 1 & 2 & 3 & 4 & 5 \\\hline \text { Gross Requirements } & & & 400 & 500 & 300 \\\hline \text { Scheduled receipts } & 0 & 0 & 0 & 0 & 0 \\\hline \text { Projected ending Inventory } & 100 & 100 & & & \\\hline \text { Net Requirements } & & & & & \\\hline \text { Planned Receipts } & & & 300 & & \\\hline \text { Planned Orders } & & & & & \\\hline\end{array}


A) 200
B) 300
C) 400
D) 500

Correct Answer

verifed

verified

Consider the product structure tree shown below: Consider the product structure tree shown below:   With a beginning inventory of ten for all components on level one, five for all components on level two, and zero for all components on level three and finished items, how many assembly E's are needed to produce 20 product X's? A) 1175 B) 1500 C) 1325 D) 1225 With a beginning inventory of ten for all components on level one, five for all components on level two, and zero for all components on level three and finished items, how many assembly E's are needed to produce 20 product X's?


A) 1175
B) 1500
C) 1325
D) 1225

Correct Answer

verifed

verified

With an inventory as shown in the table, how many assembly E's should be produced or purchased to produce 15 product X's with this product structure tree?  With an inventory as shown in the table, how many assembly E's should be produced or purchased to produce 15 product X's with this product structure tree?    \begin{array} { | l | c | c | c | c | c | c | }  \text { Item } & \mathrm { X } & \mathrm { A } & \mathrm { B } & \mathrm { C } & \mathrm { D } & \mathrm { E } \\ \hline \text { Inventory } & 5 & 15 & 20 & 8 & 6 & 17 \\ \hline \end{array}  A) 91 B) 147 C) 193 D) 225  Item XABCDE Inventory 515208617\begin{array} { | l | c | c | c | c | c | c | } \text { Item } & \mathrm { X } & \mathrm { A } & \mathrm { B } & \mathrm { C } & \mathrm { D } & \mathrm { E } \\\hline \text { Inventory } & 5 & 15 & 20 & 8 & 6 & 17 \\\hline\end{array}


A) 91
B) 147
C) 193
D) 225

Correct Answer

verifed

verified

Showing 81 - 96 of 96

Related Exams

Show Answer