Identify and briefly explain the four categories of project risks.

Correct Answer

verifed

verified

Four categories of project risks include...

View Answer

The earliest start time (ES)for an activity is the maximum of the earliest finish (EF)times for all the activities that immediately precede the activity.

Correct Answer

verifed

verified

True

Discuss the importance of establishing the scope,time frame,and resources to be allocated to a project before the project is actually started.

Correct Answer

verifed

verified

A thorough statement of the project scop...

View Answer

For controlling projects,the Schedule Performance Index (SPI)equals the cost of the work that was scheduled to have been completed by a particular date based on the original budget and project plan.

Correct Answer

verifed

verified

Table 3.7 Table 3.7    -Using Table 3.7,what is the latest start time for activity A? A) Week 0 B) Week 1 C) Week 2 D) Week 3 or later -Using Table 3.7,what is the latest start time for activity A?


A) Week 0
B) Week 1
C) Week 2
D) Week 3 or later

Correct Answer

verifed

verified

Table 3.7 Table 3.7    -Using Table 3.7,suppose activity I is delayed,taking 8 weeks to complete instead of 2 weeks.Assume all other activity times remain the same.How much longer will the total project earliest completion time become? A) 0 weeks B) 1 or 2 weeks C) 3 or 4 weeks D) 5 or 6 weeks -Using Table 3.7,suppose activity I is delayed,taking 8 weeks to complete instead of 2 weeks.Assume all other activity times remain the same.How much longer will the total project earliest completion time become?


A) 0 weeks
B) 1 or 2 weeks
C) 3 or 4 weeks
D) 5 or 6 weeks

Correct Answer

verifed

verified

Table 3.4 Table 3.4    -Using Table 3.4,what is the latest finish time for activity D? A) 4 weeks B) 6 weeks C) 8 weeks D) 10 weeks -Using Table 3.4,what is the latest finish time for activity D?


A) 4 weeks
B) 6 weeks
C) 8 weeks
D) 10 weeks

Correct Answer

verifed

verified

C

Table 3.3 Table 3.3    -Using Table 3.3,what is the minimum number of activities that would have to be delayed in order to cause an increase in the project's earliest completion date? A) 1 activity B) 2 activities C) 3 activities D) 4 or more activities -Using Table 3.3,what is the minimum number of activities that would have to be delayed in order to cause an increase in the project's earliest completion date?


A) 1 activity
B) 2 activities
C) 3 activities
D) 4 or more activities

Correct Answer

verifed

verified

The work breakdown structure is a statement of all work that has to be completed.

Correct Answer

verifed

verified

The ________ cost refers to the additional cost associated with reducing an activity time in a project network.

Correct Answer

verifed

verified

Network methods let project managers analyze the time and cost implications of resource trade-offs.

Correct Answer

verifed

verified

Table 3.8 Table 3.8    -Using Table 3.8,what is the earliest completion time of the project? A) less than or equal to 10 weeks B) greater than 10 weeks but less than or equal to 13 weeks C) greater than 13 weeks but less than or equal to 16 weeks D) greater than 16 weeks -Using Table 3.8,what is the earliest completion time of the project?


A) less than or equal to 10 weeks
B) greater than 10 weeks but less than or equal to 13 weeks
C) greater than 13 weeks but less than or equal to 16 weeks
D) greater than 16 weeks

Correct Answer

verifed

verified

Total slack can be calculated as the difference between the latest start (LS)and earliest start (ES),or by the difference between the latest finish (LF)and earliest finish (EF).

Correct Answer

verifed

verified

The earliest start time for an activity is equal to the


A) smallest earliest finish time of all of its immediate predecessors.
B) largest earliest finish time of all of its immediate predecessors.
C) smallest late start time of any of its immediate predecessors.
D) largest late finish time of all of its immediate predecessors.

Correct Answer

verifed

verified

Table 3.9 All activity times for the project are in weeks. Table 3.9 All activity times for the project are in weeks.    -Using Table 3.9,what is the expected time of completion of the project? A) less than 22 weeks B) 22 weeks C) 23 weeks D) greater than 23 weeks -Using Table 3.9,what is the expected time of completion of the project?


A) less than 22 weeks
B) 22 weeks
C) 23 weeks
D) greater than 23 weeks

Correct Answer

verifed

verified

Free slack is the amount of time that an activity's earliest finish time can be delayed without delaying the earliest start time of any activity immediately following it.

Correct Answer

verifed

verified

A precedence relationship specifies that one activity cannot start until a preceding activity has been started.

Correct Answer

verifed

verified

False

Assume that activity G has the following times: Early start time = 7 days Early finish time = 13 days Late start time = 15 days Late finish time = 21 days Which of the following statements is TRUE about activity G?


A) Activity G takes 14 days to complete.
B) Activity G has a slack time of 8 days.
C) Activity G is on the critical path.
D) Activity G takes 2 days to complete.

Correct Answer

verifed

verified

The ________ is the shortest time in which an activity can be completed if all goes exceptional well.

Correct Answer

verifed

verified

Table 3.6 Table 3.6    -Using Table 3.6,what is the slack for activity G? A) 9 weeks B) 21 weeks C) 23 weeks D) 30 weeks -Using Table 3.6,what is the slack for activity G?


A) 9 weeks
B) 21 weeks
C) 23 weeks
D) 30 weeks

Correct Answer

verifed

verified